Approval has been received to begin the projects for Lake Livingston Water Supply Corporation.
∗PHASE 1
Interconnection of Weavers Cove to the East Surface Treatment Plant.
∗PHASE 2
Interconnection of Impala Woods to the North Surface Treatment Plant.
∗PHASE 3
Line replacement at Sandy Ridge.
∗PHASE 4
Line replacement at Lake Tejas
Phase 1 of the projects is expected to begin on August 28, 2023. These project are expected to continue for 240 days (May 2024) weather permitting during this time.